Brindisi Combined Cycle Power Plant is a 1,185MW gas fired power project. It is located in Apulia, Italy. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in June 2005. Buy the profile here.
Description
The project is currently owned by EniPower with a stake of 100%.
It is a CCGT with Cogen power plant.
Development status
The project got commissioned in June 2005.
Contractors involved
Saipem was selected to render engineering procurement construction services for the gas fired power project.
Brindisi Combined Cycle Power Plant (Brindisi Combined Cycle Power Plant Block I) is equipped with Ansaldo Energia steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Brindisi Combined Cycle Power Plant (Brindisi Combined Cycle Power Plant Block I) is equipped with Ansaldo Energia V94.3A gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.
Brindisi Combined Cycle Power Plant (Brindisi Combined Cycle Power Plant Block II) is equipped with Ansaldo Energia steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Brindisi Combined Cycle Power Plant (Brindisi Combined Cycle Power Plant Block II) is equipped with Ansaldo Energia V94.3A gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.
Brindisi Combined Cycle Power Plant (Brindisi Combined Cycle Power Plant Block III) is equipped with Ansaldo Energia steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Brindisi Combined Cycle Power Plant (Brindisi Combined Cycle Power Plant Block III) is equipped with Ansaldo Energia V94.3A gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.
Ansaldo Energia supplied electric generator for the project.
Nooter/Eriksen supplied steam boiler for the Brindisi Combined Cycle Power Plant (Brindisi Combined Cycle Power Plant Block I).
Nooter/Eriksen supplied steam boiler for the Brindisi Combined Cycle Power Plant (Brindisi Combined Cycle Power Plant Block II).
Nooter/Eriksen supplied steam boiler for the Brindisi Combined Cycle Power Plant (Brindisi Combined Cycle Power Plant Block III).
For more details on Brindisi Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.