Brunot Island Combined Cycle Power Plant is a 339.9MW gas fired power project. It is located in Pennsylvania, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in June 1973. Buy the profile here.
Description
The project is currently owned by GenOn Holdings with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Peoples Gas System Inc., Dominion Energy Transmission, Inc..
Development status
The project got commissioned in June 1973.
Contractors involved
Brunot Island Combined Cycle Power Plant (Brunot Island Combined Cycle Power Plant - GT) is equipped with GE Power Frame 7E gas turbines. The phase consists of 3 gas turbines with 65.3MW nameplate capacity.
Brunot Island Combined Cycle Power Plant (Brunot Island Combined Cycle Power Plant - ST) is equipped with GE Power steam turbine. The phase consists of 1 steam turbine with 144MW nameplate capacity.
GE Power supplied electric generator for the Brunot Island Combined Cycle Power Plant (Brunot Island Combined Cycle Power Plant - ST).
Amec Foster Wheeler supplied steam boiler for the Brunot Island Combined Cycle Power Plant (Brunot Island Combined Cycle Power Plant - GT).
GenOn Holdings is the O&M contractor for thermal power project.
For more details on Brunot Island Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.