Burgenland Wind Farm_Puspok Group is a 165MW onshore repowered wind power project. It is planned in Burgenland, Austria. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. Post completion of the construction, the project is expected to get commissioned in 2023. Buy the profile here.
Description
The project is being developed and currently owned by Puspok Group. The company has a stake of 100%.
The project cost is expected to be around $291.951m.
Development status
Post completion of the construction, the project is expected to get commissioned in 2023.
Contractors involved
GE Renewable Energy will be the turbine supplier for the wind power project. The company is expected to provide 30 turbines, each with 5.5MW nameplate capacity.
The rotor blades are likely to be supplied by LM Wind Power Holding. The blade length is expected to be 158.000m.