Bursa Combined Cycle Power Plant is a 1,432MW gas fired power project. It is located in Bursa, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1996 and subsequently entered into commercial operation in November 1998. Buy the profile here.
Description
The project is currently owned by Elektrik Uretim.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
Development status
The project construction commenced in 1996 and subsequently entered into commercial operation in November 1998.
Contractors involved
ENKA Insaat ve Sanayi, Itochu and Mitsubishi Power were selected to render engineering procurement construction services for the gas fired power project.
Mitsubishi Power was selected as the turbine supplier for the Gas fired project. The company provided 2 steam turbines, each with 238MW nameplate capacity.
Mitsubishi Power was selected as the turbine supplier for the Gas fired project. The company provided 4 units of M701F gas turbines, each with 239MW nameplate capacity.
Mitsubishi Power supplied electric generator for the project.
Mitsubishi Power supplied electric generator for the project.
Mitsubishi Power supplied electric generator for the project.
Mitsubishi Power supplied steam boiler for the project.
Mitsubishi Power supplied steam boiler for the project.
Mitsubishi Power supplied steam boiler for the project.
Elektrik Uretim is the O&M contractor for thermal power project.
For more details on Bursa Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.