Campos Vellos Wind Farm is a 30MW onshore wind power project. It is planned in Galicia, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. Post completion of the construction, the project is expected to get commissioned in 2024. Buy the profile here.
Description
The project is being developed and currently owned by Greenalia Wind Power SLU. The company has a stake of 100%.
The project is expected to generate 121,567MWh of electricity. The project cost is expected to be around $43.53m.
The project will have 102.5m high towers.
Development status
Post completion of the construction, the project is expected to get commissioned in 2024.
Contractors involved
Siemens Gamesa Renewable Energy will be the turbine supplier for the wind power project. The company is expected to provide 6 units of SG 5.0-145 turbines, each with 5MW nameplate capacity.