Carlsbad Energy Center Project is a 527.5MW gas fired power project. It is located in California, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in December 2018. Buy the profile here.

Description

The project is currently owned by Clearway Energy.

It is a Gas Turbine power plant.

The project cost is $2,200m.

Development status

The project got commissioned in December 2018.

Power purchase agreement

The power generated from the project is sold to San Diego Gas & Electric under a power purchase agreement for a period of 20 years.

Contractors involved

ARB and Burns & McDonnell were selected to render engineering procurement construction services for the gas fired power project.

GE Power was selected as the turbine supplier for the Gas fired project. The company provided 5 units of LMS100-PA gas turbines, each with 105.5MW nameplate capacity.

For more details on Carlsbad Energy Center Project, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.