Castelnou Combined Cycle Power Plant is a 760MW gas fired power project. It is located in Aragon, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in July 2006. Buy the profile here.
Description
The project is currently owned by Engie with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Reserve.
Development status
The project got commissioned in July 2006.
Contractors involved
Initec Energia was selected to render engineering procurement construction services for the gas fired power project.
Mitsubishi Power was selected as the turbine supplier for the Gas fired project. The company provided 1 steam turbine with 280MW nameplate capacity.
Mitsubishi Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of M701F gas turbines, each with 240MW nameplate capacity.
Mitsubishi Power supplied Hydrogen Cooled electric generator for the project.
Mitsubishi Power supplied Hydrogen Cooled electric generator for the project.
John Cockerill Group supplied steam boiler for the project.
John Cockerill Group supplied steam boiler for the project.
For more details on Castelnou Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.