Cavriglia Solar Park is a 19MW solar PV power project. It is located in Tuscany, Italy. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in October 2011. Buy the profile here.
Description
The project was developed by Cellini General Technology Contractor.
Cavriglia Solar Park is a ground-mounted solar project which is spread over an area of 470,000 square meters.
The project generates 32,600MWh electricity and supplies enough clean energy to power 12,500 households. The project cost is $92.65m.
Development status
The project got commissioned in October 2011.
Contractors involved
Cellini General Technology Contractor was selected to render engineering procurement construction services for the solar PV power project.
Canadian Solar was selected as the supplier of the PV modules for the project. The company installed 79,400 modules at the site.
The inverters were procured from ABB Ltd (UK) for the project.
Cellini General Technology Contractor is the O&M contractor for the solar PV power project for a period of 20 years.