Cedar Bayou Steam Turbine Power Plant is a 2,295MW gas fired power project. It is located in Texas, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 1970. Buy the profile here.

Description

The project is currently owned by NRG Energy with a stake of 100%.

It is a Steam Turbine power plant. The fuel is procured from Kinder Morgan.

Development status

The project got commissioned in December 1970.

Contractors involved

Cedar Bayou Steam Turbine Power Plant (Cedar Bayou Steam Turbine Power Plant Unit I) is equipped with Siemens steam turbine. The phase consists of 1 steam turbine with 765MW nameplate capacity.

Babcock & Wilcox Enterprises supplied steam boiler for the Cedar Bayou Steam Turbine Power Plant (Cedar Bayou Steam Turbine Power Plant Unit I).

Babcock & Wilcox Enterprises supplied steam boiler for the Cedar Bayou Steam Turbine Power Plant (Cedar Bayou Steam Turbine Power Plant Unit II).

Amec Foster Wheeler supplied steam boiler for the Cedar Bayou Steam Turbine Power Plant (Cedar Bayou Steam Turbine Power Plant Unit III).

For more details on Cedar Bayou Steam Turbine Power Plant, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.