Centauro Solar PV Park is a 12MW solar PV power project. It is planned in Nuble, Chile. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. Post completion of the construction, the project is expected to get commissioned in 2023. Buy the profile here.
Description
The project is being developed and currently owned by Centauro Solar. The company has a stake of 100%.
Centauro Solar PV Park is a ground-mounted solar project which is planned over 17 hectares.
The project is expected to supply enough clean energy to power 5,000 households. The project cost is expected to be around $13.65m.
Development status
Post completion of the construction, the project is expected to get commissioned in 2023.
Power purchase agreement
The power generated from the project will be sold to Sistema Interconectado Central under a power purchase agreement, starting from 2022.
Contractors involved
Hanwha Q Cells will be the supplier of the PV modules for the solar power project. The company is expected to provide 32,433 modules each with 370W of nameplate capacity.
FIMER is likely to be the supplier of 100 of its PVS-120-TL inverters to the project site.
For more details on Centauro Solar PV Park, buy the profile here.
About Centauro Solar
Centauro Solar SpA (Centauro Solar) is a renewable energy company. It manages the Solar Centaur Photovoltaic Park in Nuble region of Chile. The project of small means of distributed generation (PMGD), includes construction and operation of a photovoltaic panel plant for the generation of electrical energy. It produces electricity using non-conventional renewable energies (ERNC) and injects into the Central Interconnected System (SIC). Centauro Solar is headquartered in Santiago, Chile.