Claus Power Plant C is a 1,300MW gas fired power project. It is located in Limburg, Netherlands. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in June 2012. Buy the profile here.

Description

The project is currently owned by RWE Generation with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant.

The project cost is $1,568.047m.

Development status

The project got commissioned in June 2012.

Contractors involved

GE Power was selected to render engineering procurement construction services for the gas fired power project.

The Gas fired project have been supplied by GE Power and Siemens.

GE Power supplied TOPAIR electric generator for the project.

GE Power supplied TOPAIR electric generator for the project.

GE Power supplied steam boiler for the project.

GE Power supplied steam boiler for the project.

GE Power is the O&M contractor for thermal power project for a period of 12 years.

For more details on Claus Power Plant C, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.