Combigolfe Combined Cycle Power Plant is a 435MW gas fired power project. It is located in Provence-Alpes-Cote dAzur, France. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2008 and subsequently entered into commercial operation in 2010. Buy the profile here.
Description
The project is currently owned by Engie with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
The project cost is $505m.
Development status
The project construction commenced in 2008 and subsequently entered into commercial operation in 2010.
Contractors involved
GE Power was selected to render engineering procurement construction services for the gas fired power project.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of GT26 gas turbine.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of STF15C steam turbine.
GE Power supplied TOPGAS electric generator for the project.
GE Power supplied steam boiler for the project.