Cristalandia I is a 30MW onshore wind power project. It is located in Bahia, Brazil. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in July 2017. Buy the profile here.

Description

The project was developed by Enel Green Power Brasil Participacoes and SoWiTec do Brasil Energias Alternativas. The project is currently owned by CGN Energy International Holdings with a stake of 99.9% and Abengoa.

The project cost is $47.288m.

Development status

The project is currently active. The project got commissioned in July 2017.

Contractors involved

Vestas Wind Systems was selected as the turbine supplier for the wind power project. The company provided 15 units of V110-2.0 MW turbines, each with 2MW nameplate capacity.

Enel Green Power Brasil Participacoes is the O&M contractor for the wind power project, commencing from the year 2017.

For more details on Cristalandia I, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.