Datang Lueyang Power Plant Unit I is a 330MW coal fired power project. It is located in Shaanxi, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in July 2007. Buy the profile here.

Description

The project is currently owned by Datang Lueyang Power Generation.

It is a Steam Turbine power plant.

The project cost is $223.898m.

The Coal fired project consists of 1 steam turbine with 330MW nameplate capacity.

Development status

The project got commissioned in July 2007.

Contractors involved

Beijing Heavy Electric Machinery Turbine Works supplied T255-460 electric generator for the project.

Beijing Heavy Electric Machinery Turbine Works supplied T255-460 electric generator for the project.

Beijing Heavy Electric Machinery Turbine Works supplied T255-460 electric generator for the project.

Babcock & Wilcox Beijing supplied steam boiler for the project.

Babcock & Wilcox Beijing supplied steam boiler for the project.

Babcock & Wilcox Beijing supplied steam boiler for the project.

For more details on Datang Lueyang Power Plant Unit I, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.