Datang Lueyang Power Plant Unit I is a 330MW coal fired power project. It is located in Shaanxi, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in July 2007. Buy the profile here.
Description
The project is currently owned by Datang Lueyang Power Generation.
It is a Steam Turbine power plant.
The project cost is $223.898m.
The Coal fired project consists of 1 steam turbine with 330MW nameplate capacity.
Development status
The project got commissioned in July 2007.
Contractors involved
Beijing Heavy Electric Machinery Turbine Works supplied T255-460 electric generator for the project.
Beijing Heavy Electric Machinery Turbine Works supplied T255-460 electric generator for the project.
Beijing Heavy Electric Machinery Turbine Works supplied T255-460 electric generator for the project.
Babcock & Wilcox Beijing supplied steam boiler for the project.
Babcock & Wilcox Beijing supplied steam boiler for the project.
Babcock & Wilcox Beijing supplied steam boiler for the project.
For more details on Datang Lueyang Power Plant Unit I, buy the profile here.