Delesto-2 Combined Cycle Power Plant is a 343MW gas fired power project. It is located in Groningen, Netherlands. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1998. Buy the profile here.
Description
The project is currently owned by Nobian Industrial Chemicals with a stake of 100%.
It is a CCGT with Cogen power plant.
Development status
The project got commissioned in 1998.
Contractors involved
GE Power was selected to render engineering procurement construction services for the gas fired power project.
GE Power was selected as the turbine supplier for the Gas fired project. The Gas fired project consists of 1 steam turbine.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of MS9001FA-50 Hz gas turbine.
GE Power supplied electric generator for the project.
For more details on Delesto-2 Combined Cycle Power Plant, buy the profile here.