Ferlach-Maria Rain is a 75MW hydro power project. It is located on Drau river/basin in Carinthia, Austria. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1971 and subsequently entered into commercial operation in 1975. Buy the profile here.
Description
The project is currently owned by VERBUND Hydro Power with a stake of 100%.
Ferlach-Maria Rain is a run-of-river project. The gross head of the project is 21.2m. The project generated 315.758 GWh of electricity.
Development status
The project construction commenced in 1971 and subsequently entered into commercial operation in 1975.
Contractors involved
Voith Hydro Holding was selected as the turbine supplier for the hydro power project. The company provided 2 units of kaplan turbines, each with 39MW nameplate capacity.
Andritz Hydro supplied 2 electric generators for the project. The generator capacity is 50 MVA.
For more details on Ferlach-Maria Rain, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.