Garrison is a 583.3MW hydro power project. It is located on Missouri river/basin in North Dakota, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1947 and subsequently entered into commercial operation in 1953. Buy the profile here.

Description

The project is currently owned by US Army Corps of Engineers with a stake of 100%.

Garrison is a reservoir based project. The penstock length is 502.92m. The penstock diameter is 7.315m. The project generated 2,600 GWh of electricity. The project cost is $300m.

Development status

The project construction commenced in 1947 and subsequently entered into commercial operation in 1953.

Contractors involved

GE Renewable Energy was selected as the turbine supplier for the hydro power project. The company provided 5 units of francis turbines.

GE Renewable Energy supplied 5 electric generators for the project. The generator capacity is 84.21 MVA.

For more details on Garrison, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.