Global 3 Escatron Combined Cycle Power Plant is a 285MW gas fired power project. It is located in Aragon, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in November 2007. Buy the profile here.

Description

The project is currently owned by Ignis Generacion with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Peakload. The fuel is procured from Enagas SA.

The project cost is $268.761m.

Development status

The project got commissioned in November 2007.

Contractors involved

Tecnicas Reunidas was selected to render engineering procurement construction services for the gas fired power project.

The Gas fired project have been supplied by GE Power and Siemens.

The electric generators for the project were procured from GE Power and Siemens.

Innovative Steam Technologies supplied steam boiler for the project.

Innovative Steam Technologies supplied steam boiler for the project.

Innovative Steam Technologies supplied steam boiler for the project.

Ignis Energia is the O&M contractor for thermal power project.

For more details on Global 3 Escatron Combined Cycle Power Plant, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.