Gok 2 is a 35.75MW onshore wind power project. It is located in Manisa, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in August 2014. Buy the profile here.

Description

The project was developed by GARET Enerji Uretim ve Ticaret. Gama Enerji, Gama Guk Sistemleri Muhendislik ve Taahhut and GAMA Holding are currently owning the project having ownership stake of 96%, 1% and 1% respectively.

The project generates 123,000MWh of electricity. The project cost is $67.425m.

Development status

The project is currently active. The project got commissioned in August 2014.

Contractors involved

GE Renewable Energy was selected as the turbine supplier for the wind power project. The company provided 13 units of 2.75-103 turbines, each with 2.75MW nameplate capacity.

For more details on Gok 2, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.