Gondo is a 57MW hydro power project. It is located in Valais, Switzerland. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1952. Buy the profile here.

Description

The project was developed by Energie Electrique du Simplon. Alpiq Holding, EnAlpin, EnBAG, FMV and Others are currently owning the project having ownership stake of 81.97%, 10.79%, 3.06%, 2.68% and 1.5% respectively.

Gondo is a reservoir based project. The gross head of the project is 470m. Gondo underwent through rehabilitation & modernization during 2012-2017. The project generated 183 GWh of electricity.

The hydro power project consists of 2 turbines.

The hydro power project consists of 1 turbine with 18.68MW nameplate capacity.

The project has 1 electric generator installed at the site. The generator capacity is 25 MVA.

Development status

The project got commissioned in 1952.

Contractors involved

Indar Electric supplied 1 electric generator for the project. The generator capacity is 25 MVA.

For more details on Gondo, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.