Granadilla Combined Cycle Power Plant is a 460.2MW oil fired power project. It is located in Canary Islands, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 2003. Buy the profile here.
Description
The project is currently owned by Union Electrica de Canarias Generacion SAU with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is diesel. In case of shortage of diesel the plant can also run on Natural Gas.
Development status
The project got commissioned in 2003.
Contractors involved
Duro Felguera was selected to render engineering procurement construction services for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit I) project. Duro Felguera was selected to render engineering procurement construction services for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit II) project. Duro Felguera was selected to render engineering procurement construction services for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit III) project. Tecnicas Reunidas was selected to render engineering procurement construction services for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit I) project. Tecnicas Reunidas was selected to render engineering procurement construction services for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit II) project. Tecnicas Reunidas was selected to render engineering procurement construction services for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit III) project. Tecnicas Reunidas was selected to render engineering procurement construction services for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase II Unit I) project. Tecnicas Reunidas was selected to render engineering procurement construction services for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase II Unit II) project. Tecnicas Reunidas was selected to render engineering procurement construction services for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase II Unit III) project.
Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit I) is equipped with GE Power MS6001FA-50 Hz gas turbine. The phase consists of 1 gas turbine with 75MW nameplate capacity.
Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit II) is equipped with GE Power MS6001FA-50 Hz gas turbine. The phase consists of 1 gas turbine with 75MW nameplate capacity.
Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit III) is equipped with Siemens ST5-V80 steam turbine. The phase consists of 1 steam turbine with 75MW nameplate capacity.
Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase II Unit I) is equipped with GE Power 6F.03 gas turbine. The phase consists of 1 gas turbine with 78.4MW nameplate capacity.
Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase II Unit II) is equipped with GE Power 6F.03 gas turbine. The phase consists of 1 gas turbine with 78.4MW nameplate capacity.
Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase II Unit III) is equipped with GE Power SC5 steam turbine. The phase consists of 1 steam turbine with 78.4MW nameplate capacity.
GE Power supplied electric generator for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit I).
GE Power supplied electric generator for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit II).
Siemens supplied electric generator for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit III).
GE Power supplied electric generator for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase II Unit I).
GE Power supplied electric generator for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase II Unit II).
GE Power supplied electric generator for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase II Unit III).
NEM Energy supplied steam boiler for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit I).
NEM Energy supplied steam boiler for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase I Unit II).
NEM Energy supplied steam boiler for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase II Unit I).
NEM Energy supplied steam boiler for the Granadilla Combined Cycle Power Plant (Granadilla CCGT Power Plant Phase II Unit II).
For more details on Granadilla Combined Cycle Power Plant, buy the profile here.