Grimsel II is a 392MW hydro power project. It is located on Oberaar river/basin in Bern, Switzerland. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project commenced construction in 1973. Buy the profile here.
Description
The project is currently owned by Kraftwerke Oberhasli.
Grimsel II is a pumped storage project. The gross head of the project is 400m. Grimsel II underwent through rehabilitation & modernization during 2012-2016. The project generated 550 GWh of electricity.
The project has 4 electric generators installed at the site. The generator capacity is 100 MVA.
Development status
The project commenced construction in 1973.
Contractors involved
Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 4 units of francis turbines.
Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 4 units of pump turbines.
For more details on Grimsel II, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.