Hunterstown Combined Cycle Power Plant is an 810MW gas fired power project. It is located in Pennsylvania, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in July 2003. Buy the profile here.
Description
The project is currently owned by Platinum Equity with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Baseload. The fuel is procured from Texas Eastern Transmission, LP.
Development status
The project got commissioned in July 2003.
Contractors involved
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 3 units of 7F.04 gas turbines, each with 165MW nameplate capacity.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of D11 steam turbine with 315MW nameplate capacity.
GE Power supplied electric generator for the project.
GE Power supplied steam boiler for the project.
NAES is the O&M contractor for thermal power project.
For more details on Hunterstown Combined Cycle Power Plant, buy the profile here.