Imaichi is a 1,050MW hydro power project. It is located on Togawa river/basin in Tochigi, Japan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1979 and subsequently entered into commercial operation in 1988. Buy the profile here.
Description
The project is currently owned by Tokyo Electric Power Co Holdings.
Imaichi is a pumped storage project. The hydro reservoir capacity is 7.07 million cubic meter. The net head of the project is 524m.
Development status
The project construction commenced in 1979 and subsequently entered into commercial operation in 1988.
Contractors involved
Toshiba Energy Systems and Solutions was selected as the turbine supplier for the hydro power project. The company provided 3 units of francis turbines, each with 350MW nameplate capacity.
Toshiba Energy Systems and Solutions supplied 3 electric generators for the project. The generator capacity is 390 MVA.
For more details on Imaichi, buy the profile here.