Irkutsk Thermal Power Station-9 is a 540MW coal fired power project. It is located in Irkutsk, Russia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. The project construction commenced in 1958 and subsequently entered into commercial operation in May 1963. Buy the profile here.
Description
The project is currently owned by Irkutskenergo with a stake of 100%.
It is a Steam Turbine with Cogen power plant that is used for Baseload. The fuel is procured from Coal of Azeisk deposit.
Development status
The project construction commenced in 1958 and subsequently entered into commercial operation in May 1963.
Contractors involved
Irkutsk Thermal Power Station-9 (Irkutsk Thermal Power Station-9 Unit I) is equipped with Leningradsky Metallichesky Zavod PT-60-130/13 steam turbine. The phase consists of 1 steam turbine with 60MW nameplate capacity.
Irkutsk Thermal Power Station-9 (Irkutsk Thermal Power Station-9 Unit II) is equipped with Leningradsky Metallichesky Zavod PT-50-130/13 steam turbine. The phase consists of 1 steam turbine with 50MW nameplate capacity.
Irkutsk Thermal Power Station-9 (Irkutsk Thermal Power Station-9 Unit III) is equipped with Leningradsky Metallichesky Zavod P-50-130/13 steam turbine. The phase consists of 1 steam turbine with 50MW nameplate capacity.
Irkutsk Thermal Power Station-9 (Irkutsk Thermal Power Station-9 Unit IV) is equipped with Leningradsky Metallichesky Zavod P-50-130/13 steam turbine. The phase consists of 1 steam turbine with 50MW nameplate capacity.
Irkutsk Thermal Power Station-9 (Irkutsk Thermal Power Station-9 Unit V) is equipped with Ural Turbine Works T-60/65 -130 steam turbine. The phase consists of 1 steam turbine with 60MW nameplate capacity.
Irkutsk Thermal Power Station-9 (Irkutsk Thermal Power Station-9 Unit VI) is equipped with Ural Turbine Works T-60/65 -130 steam turbine. The phase consists of 1 steam turbine with 60MW nameplate capacity.
Irkutsk Thermal Power Station-9 (Irkutsk Thermal Power Station-9 Unit VII) is equipped with Ural Turbine Works T-100/120-130 steam turbine. The phase consists of 1 steam turbine with 110MW nameplate capacity.
Irkutsk Thermal Power Station-9 (Irkutsk Thermal Power Station-9 Unit VIII) is equipped with Ural Turbine Works R-100-130/15 steam turbine. The phase consists of 1 steam turbine with 100MW nameplate capacity.
NPO Elsib supplied TV-60-2, Hydrogen Cooled electric generator for the project.
NPO Elsib supplied TV-60-2, Hydrogen Cooled electric generator for the project.
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the project.
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the project.
For more details on Irkutsk Thermal Power Station-9, buy the profile here.