Jajce is a 90MW hydro power project. It is located on Pliva,Vrbas river/basin in Bosnia and Herzegovina. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1954. Buy the profile here.

Description

The project is currently owned by JP Elektroprivreda Hrvatske Zajednice Herceg Bosne dd Mostar.

Jajce is a run-of-river project. The project generated 408 GWh of electricity.

Development status

The project got commissioned in 1954.

Contractors involved

Jajce (Jajce I) is equipped with Andritz Hydro kaplan turbines. The phase consists of 2 turbines with 30MW nameplate capacity.

Jajce (Jajce II) is equipped with Litostroj Power francis turbines. The phase consists of 3 turbines with 10MW nameplate capacity.

Koncar - Elektroindustrija supplied 2 electric generators for the Jajce (Jajce I). The generator capacity is 36 MVA.

Koncar - Elektroindustrija supplied 3 electric generators for the Jajce (Jajce II). The generator capacity is 12.5 MVA.

For more details on Jajce, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.