Jerico is a 32.9MW onshore wind power project. It is located in Rio Grande do Norte, Brazil. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in December 2017. Buy the profile here.

Description

The project was developed by EDP Renovaveis Brasil. China Three Gorges and EDP Renovaveis Brasil are currently owning the project having ownership stake of 49% and 45% respectively.

The project cost is $43.83m.

Development status

The project is currently active. The project got commissioned in December 2017.

Power purchase agreement

The power generated from the project is sold to Agro Energy under a power purchase agreement. The power is sold at the rate of $0.109kWh for a period of 20 years.

Contractors involved

Enercon was selected as the turbine supplier for the wind power project. The company provided 14 units of E-92 / 2,350 kW turbines, each with 2.35MW nameplate capacity.

The wind power project consists of Concrete towers supplied by Wobben Windpower Industria e Comercio. These towers are around 97m high.

For more details on Jerico, buy the profile here.