Jiangxi Guixi Power Plant is a 2,380MW coal fired power project. It is located in Jiangxi, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in September 2005. Buy the profile here.
Description
The project is currently owned by State Power Investment.
It is a Steam Turbine power plant that is used for Peakload.
Development status
The project got commissioned in September 2005.
Contractors involved
Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit I) is equipped with Shanghai Turbine N-125-135 / 535/535 steam turbine. The phase consists of 1 steam turbine with 125MW nameplate capacity.
Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit II) is equipped with Shanghai Turbine N-125-135 / 535/535 steam turbine. The phase consists of 1 steam turbine with 125MW nameplate capacity.
Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit III) is equipped with Shanghai Turbine N-125-135 / 535/535 steam turbine. The phase consists of 1 steam turbine with 125MW nameplate capacity.
Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit IV) is equipped with Shanghai Turbine Shanghai Turbine Co., Ltd. steam turbine. The phase consists of 1 steam turbine with 125MW nameplate capacity.
Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit V) is equipped with Dongfang Turbine N300-16.7 / 537 / 537-8 steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit VI) is equipped with Dongfang Turbine N300-16.7 / 537 / 537-8 steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit VII) is equipped with GE Power steam turbine. The phase consists of 1 steam turbine with 640MW nameplate capacity.
Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit VIII) is equipped with GE Power steam turbine. The phase consists of 1 steam turbine with 640MW nameplate capacity.
DEC Dongfang Electric Machinery supplied QFSN 300-2-20B electric generator for the Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit V).
DEC Dongfang Electric Machinery supplied QFSN 300-2-20B electric generator for the Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit VI).
GE Power supplied electric generator for the Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit VII).
GE Power supplied electric generator for the Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit VIII).
Dongfang Boiler Group supplied steam boiler for the Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit V).
Dongfang Boiler Group supplied steam boiler for the Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit VI).
Harbin Boiler supplied steam boiler for the Jiangxi Guixi Power Plant (Jiangxi Guixi Power Plant Unit VIII).
For more details on Jiangxi Guixi Power Plant, buy the profile here.