Jimah Project 3B Power Plant is a 2,000MW coal fired power project. It is located in Negeri Sembilan, Malaysia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in August 2019. Buy the profile here.
Description
The project was developed by Jimah East Power Sdn. Tenaga Nasional, Mitsui and The Chugoku Electric Power are currently owning the project having ownership stake of 70%, 15% and 15% respectively.
It is a Steam Turbine power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is coal. In case of shortage of coal the plant can also run on Light Fuel Oil. The fuel is procured from TNB Fuel Service Sdn. Bhd..
Development status
The project got commissioned in August 2019.
Power purchase agreement
The power generated from the project is sold to Tenaga Nasional under a power purchase agreement for a period of 25 years.
Contractors involved
Hyundai Engineering, Hyundai Engineering & Construction, IHI and Toshiba Energy Systems and Solutions were selected to render engineering procurement construction services for the coal fired power project.
Toshiba Energy Systems and Solutions was selected as the turbine supplier for the Coal fired project. The company provided 2 steam turbines, each with 1,000MW nameplate capacity.
Toshiba Energy Systems and Solutions supplied electric generator for the project.
Toshiba Energy Systems and Solutions supplied electric generator for the project.
Toshiba Energy Systems and Solutions supplied electric generator for the project.
Toshiba Energy Systems and Solutions supplied electric generator for the project.
IHI supplied steam boiler for the project.
IHI supplied steam boiler for the project.
IHI supplied steam boiler for the project.
IHI supplied steam boiler for the project.
Korea Electric Power Industrial Development and Tenaga Nasional were contracted to render operations & maintenance services for the project.
For more details on Jimah Project 3B Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.