Jinggangshan Power Plant is a 1,920MW coal fired power project. It is located in Jiangxi, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 2000. Buy the profile here.
Description
The project is currently owned by Huaneng Power International with a stake of 100%.
It is a Steam Turbine power plant.
The project generated 9,244,000MWh of electricity.
Development status
The project got commissioned in December 2000.
Power purchase agreement
The power generated from the project is sold to Jiangxi Provincial Power under a power purchase agreement.
Contractors involved
Jinggangshan Power Plant (Jinggangshan Power Plant Phase I Unit I) is equipped with Harbin Turbine steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Jinggangshan Power Plant (Jinggangshan Power Plant Phase I Unit II) is equipped with Harbin Turbine steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Jinggangshan Power Plant (Jinggangshan Power Plant Phase II Unit I) is equipped with Dongfang Turbine steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.
Jinggangshan Power Plant (Jinggangshan Power Plant Phase II Unit II) is equipped with Dongfang Turbine steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.
Harbin Electric Machinery supplied electric generator for the Jinggangshan Power Plant (Jinggangshan Power Plant Phase I Unit I).
Harbin Electric Machinery supplied electric generator for the Jinggangshan Power Plant (Jinggangshan Power Plant Phase I Unit II).
Shanghai Boiler Works supplied steam boiler for the Jinggangshan Power Plant (Jinggangshan Power Plant Phase I Unit I).
Shanghai Boiler Works supplied steam boiler for the Jinggangshan Power Plant (Jinggangshan Power Plant Phase I Unit II).
Dongfang Boiler Group supplied steam boiler for the Jinggangshan Power Plant (Jinggangshan Power Plant Phase II Unit I).
Dongfang Boiler Group supplied steam boiler for the Jinggangshan Power Plant (Jinggangshan Power Plant Phase II Unit II).
For more details on Jinggangshan Power Plant, buy the profile here.