Kandira Wind Farm is a 49.8MW onshore wind power project. It is located in Kocaeli, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in March 2021. Buy the profile here.

Description

The project was developed by RT Enerji Turizm Sanayi ve Ticaret and Saganak Enerji Yatirim Uretim ve Ticaret Anonim. RT Enerji Turizm Sanayi ve Ticaret and Turkerler Holding are currently owning the project.

The project generates 176,000MWh electricity and supplies enough clean energy to power 56,884 households, offsetting 68,038.856t of carbon dioxide emissions (CO2) a year.

The Kandira Wind Farm (Kandira Wind Farm Phase I), has 120.50m high towers.

The Kandira Wind Farm (Kandira Wind Farm Phase II), has 120.50m high towers.

Development status

The project is currently active. The project got commissioned in March 2021.

Contractors involved

Kandira Wind Farm (Kandira Wind Farm Phase I) is equipped with GE Renewable Energy 5.3-158 MW turbines. The phase consists of 2 turbines with 5.3MW nameplate capacity.

Kandira Wind Farm (Kandira Wind Farm Phase II) is equipped with GE Renewable Energy 5.3-158 MW turbines. The phase consists of 8 turbines with 4.9MW nameplate capacity.

For more details on Kandira Wind Farm, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.