Kashimbila is a 40MW hydro power project. It is located on Kastina Ala river/basin in Taraba, Nigeria. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 2018. Buy the profile here.

Description

The project was developed by SCC Nigeria and is currently owned by Government of Nigeria.

Kashimbila is a run-of-river project. The hydro reservoir capacity is 500 million cubic meter. The gross head and net head of the project are 20.5m and 17.8m respectively. The project generated 210 GWh of electricity. The project cost is $65.758m.

Development status

The project got commissioned in 2018.

Contractors involved

Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 4 units of kaplan turbines, each with 10MW nameplate capacity.

Gamesa Electric supplied 4 electric generators for the project.

For more details on Kashimbila, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.