Khursaniyah Power Plant is a 300MW gas fired power project. It is located in Eastern Province, Saudi Arabia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 2009. Buy the profile here.
Description
The project is currently owned by Saudi Arabian Oil.
It is a Gas Turbine with Cogen power plant.
Development status
The project got commissioned in 2009.
Contractors involved
Saipem was selected to render engineering procurement construction services for the gas fired power project.
Mitsubishi Power was selected as the turbine supplier for thermal power project. The project consists of 2 units of M501F turbines, each with 150MW nameplate capacity.
Mitsubishi Power supplied electric generator for the Khursaniyah Power Plant (Khursaniyah Power Plant Unit I).
Mitsubishi Power supplied electric generator for the Khursaniyah Power Plant (Khursaniyah Power Plant Unit II).
Nooter/Eriksen supplied steam boiler for the project.
For more details on Khursaniyah Power Plant, buy the profile here.