Korba West Thermal Power Station Extension is a 500MW coal fired power project. It is located in Chhattisgarh, India. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in September 2013. Buy the profile here.
Description
The project is currently owned by Chhattisgarh State Power Generation.
It is a Steam Turbine power plant.
The project cost is $466.948m.
Development status
The project got commissioned in September 2013.
Contractors involved
Bharat Heavy Electricals was selected to render engineering procurement construction services for the coal fired power project.
Bharat Heavy Electricals was selected as the turbine supplier for the Coal fired project. The company provided 1 steam turbine with 500MW nameplate capacity.
Bharat Heavy Electricals supplied electric generator for the project.
Bharat Heavy Electricals supplied steam boiler for the project.
For more details on Korba West Thermal Power Station Extension, buy the profile here.