Krasnopolyanskaya-2 is an 82MW hydro power project. It is located on Mzymta river/basin in Krasnodar Krai, Russia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2010 and subsequently entered into commercial operation in 2014. Buy the profile here.

Description

The project is currently owned by Greta Energy RU.

The net head of the project is 180m. The project generated 170 GWh of electricity. The project cost is $154.16m.

The hydro power project consists of 4 turbines, each with 20.5MW nameplate capacity.

Development status

The project construction commenced in 2010 and subsequently entered into commercial operation in 2014.

For more details on Krasnopolyanskaya-2, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.