Lista is a 71.3MW onshore wind power project. It is located in Agder, Norway. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in December 2012. Buy the profile here.
Description
The project was developed by Norsk Miljo Energi Sor. Fred. Olsen Renewables, Others, MEAG Munich Ergo AssetManagement, Keppel Infrastructure Trust and Keppel are currently owning the project having ownership stake of 51%, 16.34%, 16.33%, 8.17% and 8.16% respectively.
The project generates 290,000MWh electricity and supplies enough clean energy to power 11,000 households.
The project has 80m high towers.
Development status
The project is currently active. The project got commissioned in December 2012.
Contractors involved
Veidekke Entreprenor was selected to render engineering procurement construction services for the wind power project.
Siemens Gamesa Renewable Energy was selected as the turbine supplier for the wind power project. The company provided 31 units of SWT-2.3-93 turbines, each with 2.3MW nameplate capacity.
Siemens Gamesa Renewable Energy is the O&M contractor for the wind power project. The operation and maintenance contract commenced from 2012, for a period of 5 years.
For more details on Lista, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.