Maisan Combined Cycle Power Plant is an 840MW gas fired power project. It is located in Maysan, Iraq. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in July 2022. Buy the profile here.
Description
The project is developed and owned by Maisan Power. The company has a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
Development status
The project got commissioned in July 2022.
Contractors involved
CITIC Construction was selected to render engineering procurement construction services for the gas fired power project.
Siemens Energy was selected as the turbine supplier for the Gas fired project. The company provided 2 units of SGT5-4000F gas turbines.
Siemens Energy was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of SST5-4000 steam turbine.
Siemens Energy supplied SGen5-2000H electric generator for the project.
Siemens Energy is the O&M contractor for thermal power project for a period of 17 years.
For more details on Maisan Combined Cycle Power Plant, buy the profile here.