Mao Khe Power Plant is a 440MW coal fired power project. It is located in Quang Ninh, Vietnam. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in October 2012. Buy the profile here.

Description

The project is currently owned by Vinacomin-Power Holding.

It is a Steam Turbine power plant. The fuel is procured from Mao Khe, Trang Bach, Khe Chuoi and Hong Thai mines.

The project cost is $557m.

Development status

The project got commissioned in October 2012.

Contractors involved

Kaidi Ecological & Environmental Technology was selected to render engineering procurement construction services for the coal fired power project.

Mao Khe Power Plant (Mao Khe Power Plant Unit I) is equipped with Dongfang Turbine steam turbine. The phase consists of 1 steam turbine with 220MW nameplate capacity.

Mao Khe Power Plant (Mao Khe Power Plant Unit II) is equipped with Dongfang Turbine steam turbine. The phase consists of 1 steam turbine with 220MW nameplate capacity.

Sumitomo SHI FW Energia supplied steam boiler for the project.

For more details on Mao Khe Power Plant, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.