Marcinelle Combined Cycle Power Plant is a 381MW gas fired power project. It is located in Hainaut, Belgium. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in March 2012. Buy the profile here.

Description

The project is currently owned by TotalEnergies Centrale Electrique Marchienne au Pont with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant.

The project generated 1,200,000MWh of electricity. The project cost is $441.8m.

Development status

The project got commissioned in March 2012.

Contractors involved

Ansaldo Energia was selected to render engineering procurement construction services for the gas fired power project.

Ansaldo Energia was selected as the turbine supplier for the Gas fired project. The Gas fired project consists of 1 steam turbine.

Ansaldo Energia was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of AE94.3A gas turbine.

Ansaldo Energia supplied electric generator for the project.

Ansaldo Energia supplied electric generator for the project.

Nooter/Eriksen supplied steam boiler for the project.

Nooter/Eriksen supplied steam boiler for the project.

For more details on Marcinelle Combined Cycle Power Plant, buy the profile here.