Meri-Pori Power Plant is a 565MW coal fired power project. It is located in Satakunta, Finland. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1994. Buy the profile here.

Description

The project is currently owned by Fortum Power and Heat with a stake of 100%.

It is a Steam Turbine power plant that is used for Peakload. The power plant run on dual-fuel. The primary fuel being used to power the plant is coal. In case of shortage of coal the plant can also run on Heavy Fuel Oil.

Development status

The project got commissioned in 1994.

Contractors involved

GE Power was selected as the turbine supplier for the Coal fired project. The company provided 1 steam turbine with 565MW nameplate capacity.

GE Power supplied Hydrogen-Cooled electric generator for the project.

GE Power supplied Hydrogen-Cooled electric generator for the project.

Tampella Power supplied steam boiler for the project.

Tampella Power supplied steam boiler for the project.

For more details on Meri-Pori Power Plant, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.