Miboro 1 is a 215MW hydro power project. It is located on Sho river/basin in Gifu, Japan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1957 and subsequently entered into commercial operation in 1961. Buy the profile here.
Description
The project is currently owned by Electric Power Development.
The hydro reservoir capacity is 370 million cubic meter. The net head of the project is 192.1m.
The hydro power project consists of 2 turbines, each with 128MW nameplate capacity.
The project has 2 electric generators installed at the site. The generator capacity is 125 MVA.
Development status
The project construction commenced in 1957 and subsequently entered into commercial operation in 1961.
For more details on Miboro 1, buy the profile here.