Mirfa Open Cycle IWPP is a 360MW gas fired power project. It is located in Abu Dhabi, United Arab Emirates. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 2017. Buy the profile here.

Description

The project was developed by Mirfa International Power & Water. Abu Dhabi National Energy, Engie and Sojitz are currently owning the project having ownership stake of 60%, 20% and 20% respectively.

It is a Gas Turbine power plant.

The project cost is $341.568m.

Development status

The project got commissioned in 2017.

Contractors involved

Ansaldo Energia, Hyundai Engineering and Hyundai Engineering & Construction were selected to render engineering procurement construction services for the gas fired power project.

GE Power was selected as the turbine supplier for the Gas fired project. The company provided 4 units of GE 9E gas turbines, each with 90MW nameplate capacity.

Thomassen Energy is the O&M contractor for thermal power project for a period of 12 years.

For more details on Mirfa Open Cycle IWPP, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.