Mosenergo TEP-12 Power Plant is a 400MW gas fired power project. It is located in Moscow, Russia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1930 and subsequently entered into commercial operation in June 1941. Buy the profile here.
Description
The project is currently owned by Mosenergo with a stake of 100%.
It is a Steam Turbine with Cogen power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Fuel Oil.
The project generated 2,547,000MWh of electricity.
Development status
The project construction commenced in 1930 and subsequently entered into commercial operation in June 1941.
Contractors involved
The Gas fired project have been supplied by Leningradsky Metallichesky Zavod and Ural Turbine Works.
The electric generators for the project were procured from Electrosila and NPO Elsib.
For more details on Mosenergo TEP-12 Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.