Mosenergo TPP-26 Combined Cycle Power Plant is a 420.9MW gas fired power project. It is located in Moscow, Russia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in June 2011. Buy the profile here.
Description
The project is currently owned by Mosenergo with a stake of 100%.
It is a CCGT with Cogen power plant.
Development status
The project got commissioned in June 2011.
Contractors involved
EnergoMashinostroitelny Alliance and GE Power were selected to render engineering procurement construction services for the gas fired power project.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of GT26 gas turbine.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of STF30C steam turbine.
GE Power supplied Air-Cooled electric generator for the project.
GE Power supplied Air-Cooled electric generator for the project.
GE Power supplied steam boiler for the project.
GE Power supplied steam boiler for the project.
GE Power is the O&M contractor for thermal power project. The operation and maintenance contract commenced from 2012, for a period of 14 years.
For more details on Mosenergo TPP-26 Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.