Mount Keith Solar PV Park is a 27.4MW solar PV power project. It is planned in Western Australia, Australia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. The project construction is likely to commence in 2022 and is expected to enter into commercial operation in 2023. Buy the profile here.
Description
The project is being developed and currently owned by TransAlta.
Mount Keith Solar PV Park is a ground-mounted solar project.
The project cost is expected to be around $29.866m.
The solar power project consists of 51,000 modules.
Development status
The project construction is expected to commence from 2022. Subsequent to that it will enter into commercial operation by 2023.
Power purchase agreement
The power generated from the project will be sold to BHP under a power purchase agreement.
Contractors involved
juwi Renewable Energy is expected to render engineering procurement construction services for the solar PV power project.
For more details on Mount Keith Solar PV Park, buy the profile here.
About TransAlta
TransAlta Corp (TransAlta) is an electricity generation company. It owns, operates and develops a divergent fleet of electricity generation assets. It generates electricity from a contracted portfolio of assets using diverse sources such as thermal coal, natural gas, hydro, wind and geothermal. TransAlta's service portfolio includes commercial and industrial energy services, wholesale energy solutions, green energy sustainable options and energy management services. It supplies power to municipalities, large and medium industries, businesses and utility customers. It is a major producer of wind power in Canada and hydro-electric power in Alberta. The company has operations and generation facilities in the US, Canada and Australia. TransAlta is headquartered in Calgary, Alberta, Canada.