Munera I is a 39.6MW onshore wind power project. It is located in Castile-La Mancha, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in February 2007. Buy the profile here.

Description

The project is currently owned by Ventient Energy with a stake of 100%.

The project cost is $85.774m.

Development status

The project is currently active. The project got commissioned in February 2007.

Contractors involved

Vestas Wind Systems was selected as the turbine supplier for the wind power project. The company provided 22 units of V90-1.8 MW turbines, each with 1.8MW nameplate capacity.

Ingeteam Corporacion is the O&M contractor for the wind power project. The operation and maintenance contract commenced from 2017, for a period of 3.5 years.

For more details on Munera I, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.