Neckeherdim-Paur is an 80MW hydro power project. It is planned on Yarkun river/basin in Khyber Pakhtunkhwa, Pakistan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. The project construction is likely to commence in 2026 and is expected to enter into commercial operation in 2028. Buy the profile here.
Description
The project is being developed and currently owned by Private Power and Infrastructure Board.
Neckeherdim-Paur is a run-of-river project. The gross head of the project will be 341m. The project is expected to generate 321 GWh of electricity.
The hydro power project consists of 2 units of pelton turbines.
Development status
The project construction is expected to commence from 2026. Subsequent to that it will enter into commercial operation by 2028.
For more details on Neckeherdim-Paur, buy the profile here.
About Private Power and Infrastructure Board
Private Power and Infrastructure Board (PPIB) promote private sector participation in the power sector of Pakistan.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.