Norther Wind is a 369.6MW offshore wind power project. The project is located in North Sea, Belgium. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2018 and subsequently entered into commercial operation in June 2019. Buy the profile here.
Description
The project was developed by Norther. Elicio, Diamond Generating Europe and Eneco Wind Belgium are currently owning the project having ownership stake of 50%, 25% and 25% respectively.
The wind turbines in the project are installed on fixed foundations. An array of monopile foundations feature in the project.
The project generates 1,400,000MWh electricity and supplies enough clean energy to power 400,000 households.
Development status
The project is currently active. The project construction commenced in 2018 and subsequently entered into commercial operation in June 2019.
Power purchase agreement
Eneco Holding and Engie are the power offtakers from the project.
Contractors involved
Vestas Offshore Wind was selected as the turbine supplier for the wind power project. The company provided 44 units of V164-8.0 MW Offshore turbines, each with 8.4MW nameplate capacity.
For more details on Norther Wind, buy the profile here.