Odayeri Landfill Power Plant is a 49.6MW biopower project. It is planned in Istanbul, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the partially active stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in December 2008. Buy the profile here.
Description
The project is being developed and currently owned by Ortadogu Energy.
The process of landfill will be adopted in this project to release the stored energy from the feed. Landfill gas will be used as a feedstock to power the project.
Development status
Post completion of the construction, the project is expected to get commissioned in December 2008.
Contractors involved
Odayeri Landfill Power Plant (Odayeri Landfill Power Plant-2 (Phase-I)) will be equipped with Turboden turbine. The phase consists of 1 turbine with 2.3MW nameplate capacity.
Odayeri Landfill Power Plant (Odayeri Landfill Power Plant-2 (Phase-II)) will be equipped with Turboden turbine. The phase consists of 1 turbine with 2.3MW nameplate capacity.
Odayeri Landfill Power Plant (Odayeri Landfill Power Plant-1) will be equipped with Caterpillar Energy Solutions engines. The phase consists of 4 engines, each with 1.2MW nameplate capacity.
Odayeri Landfill Power Plant (Odayeri Landfill Power Plant-1) will be equipped with INNIO Jenbacher engines. The phase consists of 28 engines, each with 1.4MW nameplate capacity.
For more details on Odayeri Landfill Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.