Oraison (Canal d’) is a 196.8MW hydro power project. It is located on Durance river/basin in Provence-Alpes-Cote dAzur, France. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1959 and subsequently entered into commercial operation in 1962. Buy the profile here.

Description

The project is currently owned by Electricite de France with a stake of 100%.

Oraison (Canal d') is a reservoir based project.

The hydro power project consists of 3 turbines, each with 65.6MW nameplate capacity.

Development status

The project construction commenced in 1959 and subsequently entered into commercial operation in 1962.

For more details on Oraison (Canal d'), buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.